TransAlta to mothball Battle River units in 2027: What Alberta businesses should know

25 November 2026

TransAlta plans to temporarily mothball Battle River Units 4 and 5 beginning March 1, 2027. The company has also extended the existing mothball outage for Sundance 6.

The changes affect when these generating units are expected to be available to Alberta’s electricity market. However, the announcement does not mean the facilities are being permanently retired, nor does it establish that electricity prices will increase.

For Alberta businesses, the update is best viewed as one of several supply-side developments to monitor when evaluating future electricity budgets and procurement decisions.

What is the TransAlta announcement about?

On November 2, 2026, TransAlta notified the Alberta Electric System Operator (AESO) that Battle River Units 4 and 5 would be mothballed effective March 1, 2027, for a period extending up to January 1, 2029.

TransAlta said the Battle River units would remain available and fully operational until the mothballing takes effect. The company also extended the mothballing of Sundance 6 for a period extending up to April 1, 2029. 

The corresponding AESO notices describe the operating periods as follows:

  • Battle River Unit 4 & 5: Mothballed from March 1, 2027, through December 31, 2028
  • Sundance 6: Existing mothball outage extended through March 31, 2029

Sundance 6 has been under an existing mothball outage since April 1, 2025. Its previous outage period was scheduled to end March 31, 2027. 

How much generation is involved?

Current AESO data lists Battle River Unit 4 at 155 megawatts and Battle River Unit 5 at 395 megawatts. Together, the units represent 550 MW of maximum capability.

Sundance 6 is listed at 401 MW. Because Sundance 6 is already mothballed, its extension does not represent an additional 401 MW being removed from the market in 2027. Instead, it means the unit is expected to remain unavailable for longer than previously scheduled. 

These figures describe each unit’s maximum capability. They should not be interpreted as the amount of electricity the units would otherwise produce continuously or as a direct measure of the announcement’s effect on market prices.

The announcement alone is not enough to determine how Alberta electricity prices will change

What does mothballing mean?

In this context, mothballing means temporarily removing a generating unit from service while preserving the possibility of returning it to operation.

TransAlta said it retains the flexibility to bring the units back into service if market fundamentals improve or suitable contracting opportunities are secured. Any return would be subject to AESO notification and operating requirements, including the return-to-service period declared for each unit. Under AESO rules, that period can be up to six months.

Why is TransAlta mothballing the units?

TransAlta described mothballing Battle River Units 4 and 5 as an economic decision.

During its third-quarter earnings call, management said the units currently have very low capacity factors and also operated at low capacity factors last year.

Mothballing allows TransAlta to reduce near-term costs while preserving the facilities for potential future demand or contracting opportunities.

Alberta’s average spot power price was $36/MWh in the third quarter of 2026, compared with $51/MWh during the same period in 2025. TransAlta attributed the year-over-year decline primarily to milder weather.

These pricing results provide relevant market context. However, TransAlta did not identify lower third-quarter spot prices alone as the reason for its decision.

TransAlta also reported an Alberta realized merchant power price of $95/MWh for the quarter. This figure included the effects of the company’s merchant sales, derivatives, trading activities and portfolio optimization, so it is not directly comparable to the average AESO spot price.

Will the change affect Alberta electricity prices?

The announcement alone is not enough to determine how Alberta electricity prices will change in 2027 or beyond.

Battle River Units 4 and 5 are expected to remain available until the mothball period begins. Once it takes effect, 550 MW of maximum capability is scheduled to become unavailable unless TransAlta changes its plans or returns the units to service.

The AESO incorporated the Battle River and Sundance mothball notices into its updated November 2026 Long-Term Adequacy Report. This confirms that the changes affect Alberta’s forward supply outlook, but the report does not establish that the mothballing will produce a specific electricity-price outcome. 

Future wholesale prices will depend on the broader balance between supply and demand, including:

  • Customer demand and weather
  • Planned and unplanned generator outages
  • Natural gas prices
  • Wind and solar production
  • Electricity imports and exports
  • New generation and storage additions
  • Changes to market rules
  • The timing of data-centre and other large-load connections

DNE’s October 2026 Alberta market update identifies the TransAlta announcement as one development affecting the province’s evolving supply and contracting outlook, rather than treating it as a stand-alone price forecast. 

What should Alberta businesses do?

Businesses do not need to change their electricity strategy based on this announcement alone. Instead, they can incorporate it into a broader review of market conditions, contract timing, budget requirements and risk tolerance.

Useful steps may include:

  • Reviewing when existing electricity contracts expire.
  • Comparing fixed, floating and blended purchasing options.
  • Stress-testing budgets against a range of potential market prices.
  • Monitoring AESO supply additions, outages and regulatory changes.
  • Assessing decisions based on operational needs rather than reacting to one market announcement.

Key takeaways

  • TransAlta plans to mothball Battle River Units 4 and 5 beginning March 1, 2027.
  • The two Battle River units have a combined maximum capability of 550 MW.
  • Sundance 6 is already mothballed, and its outage has been extended through March 31, 2029.
  • TransAlta retains the flexibility to return the units to service, subject to AESO notification and return-to-service requirements.
  • The facilities have not been announced as permanently retired.
  • The announcement does not, by itself, establish that Alberta electricity prices will rise.
  • Alberta businesses should assess the development as one factor within the province’s broader electricity-market outlook.